Sioux Falls Main Pump Station Increases Collection Capacity

    Market

  • Public Utilities

    Services

  • Construction
  • Engineering
  • Wastewater
  • Water

    Locations

  • Sioux Falls, South Dakota

The Sioux Falls Main Pump Station (MPS) project consists of the design, bidding, and construction of a wastewater pump station that pumps 90% of Sioux Falls wastewater to the Water Reclamation Facility. The MPS is a critical infrastructure facility that increases the Sioux Falls wastewater collection system capacity in conjunction with improvements to the outfall sewer and Water Reclamation Facility. The MPS is the largest wastewater pump station in South Dakota and provides additional sewer capacity to accommodate future development in Sioux Falls.

The Sioux Falls Main Pump Station replaces the existing Brandon Road Pump Station, which is approximately 40 years old and would have required updates to increase flow and improve maintenance access, functionality, standby power, and safety. The MPS has a peak design capacity of 65 mgd, and the capability to add a pump to increase the flow to 90 mgd. Screening facilities include two mechanical screens, a bypass channel, and a channel for a future screen to be added to increase flow capacity. Four dry-pit pumps are located in the pump room, sized for an individual peak flow of 15,000 gpm at 128’ TDH, and use 600 hp motors controlled by variable frequency drives. Space for a fifth pump is provided to increase flow in the future. The pump room includes maintenance provisions for servicing pumps, including a bridge crane and an open mezzanine to allow access to the piping header.

The preliminary design included site evaluation of the existing City property and adjacent sites for relocation of the pump station, considering constructability, staging area, flood plain, property cost, traffic impacts, and existing utilities. The final design included a surge analysis conducted to protect the piping system from high and low-pressure conditions and evaluate surge tanks and surge relief valves. The design also included structural, architectural, mechanical, electrical, and instrumentation design. The construction of the Sioux Falls Main Pump Station took nearly 2.5 years and encountered multiple challenges, such as site flooding, pandemic-related labor delays, and supply chain issues.

The Main Pump Station project provided the following key impacts and innovations:

  • The Main Pump Station serves 90% of Sioux Falls. Expansion of the facility will enable future development in Sioux Falls.
  • Innovative engineering approaches to wet well design, corrosion protection, and electrical switchgear control were incorporated in the design.
  • The 65 mgd facility is the largest wastewater pump station in South Dakota. The capacity, ability for future expansion, and longevity of design choices will serve Sioux Falls for many years.
Awards

South Dakota Engineering Society – Eastern Chapter Project of the Year Award

American Society of Civil Engineers – South Dakota Outstanding Civil Engineering Achievement

 

Work With Us
Work With Us
Contact Our Team
For more than 100 years, HR Green has been dedicated to providing the services that our clients need to achieve success.